/ CASE STUDY · LOGISTICS

Northlane Group

Eleven networks, four help desks and one freight season that could not be interrupted.

Client

Northlane Group

Estate

1,400 seats · 62 sites

Duration

9 months

Services

Network, managed IT, DR

Status

Ongoing since 2023

0 

Planned outages across 62 site cutovers.

-58%

Monthly incident volume, measured against the 2023 baseline.

4→1

Help desks consolidated into a single 24/7 route.

The constraint

A decade of acquisitions, none of them integrated.

Northlane had grown by buying regional hauliers and leaving their IT alone. By 2023 that meant eleven addressing schemes that overlapped, four service desks with different ticketing tools, and depot managers who kept a personal list of which engineer to phone. Nothing was broken enough to justify a shutdown, and everything was fragile enough to make one likely.

The board's requirement was blunt: fix it without touching September through December, when the network moves 40% of its annual volume. That ruled out a big-bang consolidation and any approach that could not be reversed inside a shift.

What we did

01

Mapped the real estate

Six weeks of passive flow analysis at every depot. It found 29 devices with no owner, three site-to-site tunnels nobody could account for, and a warehouse management server that had not been patched since 2019.

02

Built the target in parallel

A new SD-WAN core stood up alongside the old estate, with two pilot depots running on it for a full month before anything else moved. Rollback was a routing change, tested weekly.

03

Migrated in waves of six

Six depots per fortnight, always mid-week, always with a named engineer on site and the depot manager's mobile in the runbook. Freight season was left untouched; the programme paused for fourteen weeks by design.

04

Folded four desks into one

The regional desks were retired last, once the network they supported no longer existed. Twelve of the seventeen staff moved into Northlane's new applications team; the rest transferred to our operations centre.

The thing I did not expect was how boring it became. Nine months of change and the only calls I got were the scheduled ones telling me a depot had finished early.

Marcus Feld
CTO, Northlane Group

Where it stands

Three years in, still measured quarterly.

Northlane now runs on our Managed tier with a named team of five. The quarterly review is presented to their board with the same baseline we established in 2023, which is why the numbers below are comparable rather than flattering.

Mean time to resolution
2h 10m
Patch coverage across fleet
98.4%
Recovery time objective, met
4 hours
Annual infrastructure spend removed
$740K